Client: Harry Gwala
Location: Sisonke District
Scope of work: Construction of Disaster Management Centre
Completion date: 26/11/2016
Capital costs: R10 974 900.48
BACKGROUND
DESCRIPTION
The works consisted of the following activities
- Drainage is the removal of excessive water from the soil profile.
- Pipe subsoil drains is constructed in accordance with this specification and in conformity with the lines, grades and cross-sections shown on drawings provided by the client.
- The work shall include: the construction of trenches, the supplying and laying of perforated pipes of the specified type and size; the jointing of the pipes; the supplying and compacting of approved backfilling materials; the construction of connecting and outlet drains; the supply of all materials; labour, plant, tools and transport required for the proper completion of the contract.