INSTALLATION OF SUBSOIL CUT-OFF BARRIERS

CONSTRUCTION OF NTININI BRIDGE 3537
April 4, 2017
INSTALLATION OF SUBSOIL DRAINAGE IN THE PLANT AREA
April 4, 2017

Client: Foskor
Location: Richards Bay
Scope of work: Installation of Subsoil Cut-Off Barriers South of the Plant
Completion date: 30/08/2013
Capital costs: R15 724 542.65

BACKGROUND

Ukhasi Construction was appointed by Foskor for the Installation of Subsoil Drainage in the plant area.

DESCRIPTION

The works consisted of the following activities

  • Drainage is the removal of excessive water from the soil profile.
  • Pipe subsoil drains is constructed in accordance with this specification and in conformity with the lines, grades and cross-sections shown on drawings provided by the client.
  • The work shall include: the construction of trenches, the supplying and laying of perforated pipes of the specified type and size; the jointing of the pipes; the supplying and compacting of approved backfilling materials; the construction of connecting and outlet drains; the supply of all materials; labour, plant, tools and transport required for the proper completion of the contract.