REPAIR OF PAVEMENT LAYER WORKS ON NATIONAL ROUTE

ROUTINE ROAD MAINTENANCE ON NATIONAL ROUTE 2 SECTION 23TO26
April 4, 2017
IMPLEMENTATION OF MTUBATUBA CBD UPGRADE PHASE 1
April 4, 2017

Client: Sanral (Penny Furthing)
Location: N2
Scope of work: Repair of pavement layer works on National Route 2
Completion date: 31/01/2012
Capital costs: R5 162 455.80

BACKGROUND

Ukhasi Construction was appointed by Sanral through Penny Furthing, the main contractor, in order to carry out our road repairs on some sections of N2 and N3 as and when required over a period of two years.

DESCRIPTION

Maintenance of the freeway is made up of the following scope

  • Survey, evaluate, determine, and verify the existing conditions within the designated project work area.
  • Work closely with the Sanral staff to coordinate traffic detours and traffic control.
  • Sanral shall provide final approval of the traffic control plan prior to executing the work.
  • Prepare the site, traffic signage, and secure the area from public access for the duration of the work.
  • Saw cut and remove the existing asphalt paving in the area as designated in the contract drawings.
  • Re-compact the existing base material to 95% compaction.
  • Should the failure only affect the surface, then a slurry seal is applied.