Client: Sanral (Penny Furthing) Location: N2 Scope of work: Repair of pavement layer works on National Route 2 Completion date: 31/01/2012 Capital costs: R5 162 455.80 […]
Client: Cogta Location: Mtubatuba Scope of work: Mtubatuba CBD upgrade phase 1 Completion date: Current Capital costs: R15 000 000.00 BACKGROUND uMtubatuba is one of the […]
Client: Cerimele (Umgeni Water) Location: Midmar Scope of work: Midmar Raw Water Pipeline Construction Completion date: Current Capital costs: R11 146 610.69 BACKGROUND Due to the […]
Client: Harry Gwala Location: Sisonke District Scope of work: Construction of Disaster Management Centre Completion date: 26/11/2016 Capital costs: R10 974 900.48 BACKGROUND DESCRIPTION The works […]
Client: Department of Transport Location: Nquthu Scope of work: construction of Ntinini Bridge 3537 Completion date: Current Capital costs: R16 146 610.69 BACKGROUND The Department of […]
Client: Foskor Location: Richards Bay Scope of work: Installation of Subsoil Cut-Off Barriers South of the Plant Completion date: 30/08/2013 Capital costs: R15 724 542.65 BACKGROUND […]
Client: Foskor Location: Richards Bay Foskor Plant Scope of works: Installation of subsoil drainage in the Plant area Completion date: 29/06/2013 Capital cost: R24 761 969.93 […]